BS 6622 XLPE MDPE 6.35/11 (12)kV Cable | ||
Voltage: | 6.35/11 (12)kV | |
Structure: | Conductor | Class 2 Stranded Copper |
Insulation | XLPE (Cross-Linked Polyethylene) | |
Screen | Individual copper wire screen | |
Jacket | MDPE (Medium Density Polyethylene) |
Power cables for power networks, underground and in cable ducting. Suitable for direct burial.
6.35/11 (12)kV
Fixed: 0°C to +90°C
0°C to +90°C
12 x overall diameter
(10 x overall diameter where bends are positioned adjacent to a joint or terminations provided that the bending is carefully controlled by the use of a former)
BS 6622, IEC 60502-2, IEC/EN 60228
Class 2 stranded copper conductor
Semi-conductive XLPE (Cross-Linked Polyethylene)
XLPE (Cross-Linked Polyethylene)
Semi-conductive XLPE (Cross-Linked Polyethylene)
Water blocking tape
Semi-conductive XLPE (Cross-Linked Polyethylene)
Individual copper wire screen
PET (Polyethylene Terephthalate) fibres
Binding tape
PVC (Polyvinyl Chloride)
SWA (Steel Wire Armoured)
MDPE (Medium Density Polyethylene)
SHEATH COLOUR | NO. OF CORES | NOMINAL CROSS SECTIONAL AREA | NOMINAL DIAMETER mm | NOMINAL WEIGHT | ||
mm2 | Under Armour | Over Armour | Overall | kg/km | ||
Black | 3 | 185 | 64.4 | 69.4 | 76 | 12600 |
Our team is available 24/7 to respond to customer inquiries and issues. Most issues can be resolved within 8 hours.
Generally, we can deliver regular machines to customers immediately within 7-30 days.
Our team is available 24/7 to respond to customer inquiries and issues. Most issues can be resolved within 8 hours.
Sampling test items: cable conductor DC resistance; finished cable withstand voltage test;conductor single wire diameter and deviation;insulation average thickness, thinnest point;The sheathed average thickness and thinnest point
Sampling test items: cable conductor DC resistance; finished cable withstand voltage test;conductor single wire diameter and deviation;insulation average thickness, thinnest point;the sheathed average thickness and thinnest poin;change rate of tensile strength and elongation of insulation and sheath before and after aging;insulated wire core withstand voltage test;hot extension test;ozone resistance test;finished cable flexure test, etc.
1.The purpose of the performance acceptance test is to verify whether all the performance of the contract products meet the requirements
2.The location of the performance acceptance test is the purchaser’s site
3.The performance acceptance test shall be carried out within 6 months after the 168-hour full load trial operation of the product, and the specific test time shall be determined by both parties through negotiation.
4.Installation of measuring points, primary components and local instruments required for performance acceptance test shall be provided by the supplier and cooperated by the demander. The supplier shall also provide the technical cooperation and personnel cooperation required for the test.
5.Content of performance acceptance test
In accordance with supplier quality assurance and test requirements.
6.Criteria for performance acceptance test
In accordance with supplier's quality assurance and test requirements.
7.The performance acceptance test shall be conducted by the demander and participated by the supplier. The test program shall be provided by the demander and determined after discussion with the supplier. The specific test shall be completed by the testing department approved by both parties.
8.Confirmation of performance acceptance test results
The performance acceptance test report shall be prepared by the testing unit, and the conclusions of the report shall be accepted by both parties. If there is any disagreement between the two parties on the results of the test, the two parties shall settle it through negotiation. If no agreement can be reached, it shall be submitted to the superior departments of both parties for negotiation.
9.When a performance acceptance test is conducted, if a party fails to send personnel to participate in the test after receiving the test notice from the other party, it shall be deemed to have agreed to the acceptance test results.
1.Supervise manufacturing basis
Refer to the former Ministry of power Industry, Ministry of Machinery Industry issued by the electricity Office (1995) No. 37 "Interim Provisions for the quality supervision of large power equipment", "General representative group working Regulations in large power equipment manufacturers"
2.Manufacturing supervision method
Document witness, on-site witness and shutdown pending inspection, namely R point,W point , and H point.
After each manufacturing supervision content is completed, the supplier and the manufacturing supervision representative will complete the signature procedures on the witness form. The supplier shall submit one copy to the demander's manufacturing supervision representative.
R point:The supplier only needs to provide items of inspection or test records or reports, that is, document evidence.
W point:Inspection or test items attended by the purchaser’s manufacturing supervision representative, i.e. on-site witness
H point: When the supplier stops to wait for the inspection or test of the buyer's supervision representative, that is, the project is stopped for inspection.
Upon receipt of the witness notice, the demander shall promptly send a representative to the site of the supplier's inspection or test to participate in on-site witness or stop work for inspection. If the representative of the demander cannot attend on time, point W can be automatically converted to point R, but if point H is not agreed to be converted to point R by written notice of the demander, the supplier will not transfer to the next process and agree with the demander to change the witness time. If the buyer is still unable to participate on time after the change, the H point will be automatically converted to R point.
3. Requirements for suppliers to cooperate with manufacturing supervision
3.1 The supplier has the obligation to cooperate with the demander's manufacturing supervision and provide relevant information in a timely manner without incurring any costs.
3.2 The Supplier shall provide the demander's supervision representative with the convenience of work and life
3.3 The supplier shall inform the Buyer's representative of the equipment supervision project and time before witnessing the site or stopping work for inspection..
3.4 Demander's supervision representative has the right to check (borrow) the technical information related to the contract supervision equipment. If demander considers it necessary to copy and file, the supplier shall provide convenience.
3.5 The supplier shall provide the inspection and test records and reports to the supervision representative of the demander after the witness.
Our team is available 24/7 to respond to customer inquiries and issues. Most issues can be resolved within 8 hours.
Generally, we can deliver regular machines to customers immediately within 7-30 days.
Our team is available 24/7 to respond to customer inquiries and issues. Most issues can be resolved within 8 hours.